| |
Introduction
| Site Economics | System
Economics
Introduction
Over
one million reciprocating and combustion turbine units
are installed worldwide, validating the practical
and economic merits of DE resources. These units are
principally installed as backup generation to mitigate
the impact of a grid power failure. Deployment of
other technologies, such as wind and solar, are increasing
as capital and operating costs continue to drop rapidly.
DE units are typically installed with one for more
of the following criteria in mind:
-
The cost of backup power is low compared to the
cost of an outage
-
Cost per kWh is competitive when compared to grid
power costs
-
The cost per kWh is reasonable compared to unanticipated
price spikes
-
Renewable energy DE units are environmentally superior
These
issues are explored more thoroughly in the Site
Economics section below. It is important to note,
however, that there are direct and indirect economic
benefits that accrue from the deployment of DE technologies.
This site mostly focuses on the direct benefits, but
it is appropriate to note that avoided costs, like
delayed central power generation construction, delayed
substation upgrades, or reduced emissions, provide
benefits to all citizens.
Site
and system economics are affected by a number of non-economic
factors. One of the more important examples is in
the restructuring of electricity markets. In many
places in the world - including the United States
- governments are experimenting with privatizing or
deregulating the utilities. The most visible results
of these actions is that utilities are being segmented
into generation, transmission, and distribution entities.
This disaggregation of costs can have the following
effects:
-
Previously
hidden costs become more visible
-
Costs
become more variable for different customer classes
-
The
true cost of power per customer segment becomes
more transparent, leading to new incentives for
DE.
Disaggregation
can also make it more difficult to internalize all
the costs and benefits of DE. It is not always immediately
clear who will benefit and who will be burdened by
a restructured energy industry. Similarly, DE can
either provide benefits or impose costs on participants
in all three sectors (generation, transmission, and
distribution) of the disaggregated industry. Table
1 depicts opportunities and barriers to DE, and presents
policy recommendations to ensure benefits.
Table
1: Opportunities and Barriers
| Opportunities |
Barriers |
Recommendations |
| Increased
DE use can lead to lower electricity cost, higher
net efficiency, and cost-effective peak load reduction.
|
Fully
regulated utilities and a lack of statistics on
reliability hide the true cost of electricity
to end users. |
Better
understanding of DE economics vs. grid supplied
power is required. Additionally, increased use
will reduce capital costs of technologies. |
| If
utilities and owners of DE work together, the
economic benefits can accrue to each other as
well as to consumers and society at large. |
Net
metering programs need to be expanded. |
Increase
the trend at policy making and regulatory levels
to create uniform and non-discriminatory business
practices. |
Site
Economics
Before
a DE project is started, users will need to determine
whether the expected cost savings or increased profits
will meet their specific financial goals. A site-specific
project analysis should include a fundamental understanding
of the site energy needs, a determination of how well
the current energy source is addressing those needs,
the value proposition of installing a system that
better meets those needs, and a decision regarding
the acceptable means of financing the project. If
there are non-financial goals, their relative importance
should also be determined. The good news is that although
the evaluation process requires a thorough understanding
of site energy requirements, it is not necessary to
be an expert in DE technologies.
Typical
generation project costs and associated efficiencies
are provided in Table 2 below. DE manufacturers are
working towards making DE technologies "plug
and play," but for now, most systems installed
today are at least somewhat customized. Due to site-specific
needs and infrastructure, there are wide variations
in cost per kW output and total installed cost. Generalized
cost figures should only be used for preliminary screening
purposes. It is important to obtain an estimate from
a qualified contractor or, for complex installations,
to hire a consultant experienced in DE system design
to develop an estimate. The Discussion
Forum can be used to ask other DE customers for
references on consultants or contractors.
The
process for developing site economics is complex,
but the following steps provide an approach to gaining
a basic understanding of the value of DE for a typical
site:
1.
Understand Site Needs
a.
Determine site energy usage for the past several
years (kWh)
b. Review the current cost of electric power
c. Review current fuel costs (natural gas, diesel,
fuel oil)
d. Evaluate site energy goals and the role DE might
play, which include answers to such questions as:
i.
Are costs the number one criterion?
ii. For businesses, is energy used mostly during
the day (retail hours), two shifts per day, or
is it required 24 hours per day?
iii. Will the DE resource be needed to cover 100%,
or a portion of the maximum load?
iv. How important is reliability? Is an uninterruptible
power supply required?
v. What fuel choices are available to you (e.g.,
natural gas, propane, heating oil, solar, wind,
diesel)?
vi. How much space is available to house the equipment?
2.
Determine which investment analysis makes most sense
a.
Simple payback - A basic, but widely used method,
of dividing the investment by the periodic project
savings. This allows calculating how many months
it requires to recover the initial investment.
b. Net Present Value (NPV) - This method converts
future costs and revenues to today's money to allow
comparison to the DE buyer's internal cash cost,
or required rate of return. A positive number indicates
that the project will have a positive return.
c. Life cycle costs (LCC) - Utilizes NPV, but instead
of analyzing a required rate of return, LCC only
analyzes the costs associated with the life of project.
The lowest LCC is preferred.
d. Internal Rate of Return (IRR) - Also derived
from NPV, however, this approach involves varying
the discount rate until NPV goes to zero. A project
in with an IRR greater than your required rate of
return is worth pursuing.
3.
Select the possible technologies that meet site requirements
a.
The DE calculator can
be used to narrow down the technologies that are
applicable.
b. Approximate costs are contained in the DE calculator.
For exact costs to meet specific needs, utilize
the contact information
supplied by the DE calculator for each manufacturer
or use the additional links to contact manufacturers
who are not yet included in the product database
directly. The manufacturer or associated installer
can provide a firm turnkey price.
4.
Calculate the site economics (The simple payback method
is used in the example calculation provided below):
a.
Determine the current cost of electricity and thermal
energy from utility bills.
i.
Electricity cost calculation for continuous 100
kW load:
1.
Usage (kW) x Rated Cost for Output ($/kWh) x Period
(hrs/yr)
2. 100 kW x $0.11/kWh x 8760 hrs/yr= $96,360/yr
ii.
Thermal energy fuel cost calculation for 500 lb/hr
of steam produced on site using a natural gas fired
boiler with 80% efficiency:
1.
Steam Usage (lb/hr) x [1/Heat Content of Steam
(lb/btu)] x [1/Boiler Efficiency] x Price Fuel
($/thousand ft3)) x Energy Content of Fuel (btu/
ft3) x Period (hrs/yr)
2. 500 lb steam/hr x 1000 btu/lb steam x [1/0.8]
x $3.10/thousand ft3 natural gas x [1 thousand
ft3 gas/1,048,000 btu] x 8760 hrs= $16,195
iii.
Total energy cost calculation: $96,360 + $16,195
= $112,555
b.
Determine projected cost of DE combined heat and power
produced from a natural gas fired 100 kW microturbine
combined heat and power unit, also providing the required
500 lbs/hr steam.
i.
Determine the cost of thermal energy supplied by
turbine (Note: Fuel flow can be obtained from the
vendor or calculated from either the unit output
and heat rate or the efficiency and the heat content
of the fuel being used.):
1.
Fuel Flow Output (thousand btu/hr) x Natural Gas
Heat Value Correction x Price Fuel ($/thousand
ft3) x Energy Content of Fuel (thousand ft3/btu)
x Period (hrs/yr) (Note: the Natural Gas Heat
Value Correction takes into account the heat lost
to water vapor formed during combustion, which
is not taken into account with the Lower Heating
Value (LHV) number reported in the microturbine
manufacturer's specifications for the unit. This
Correction converts the LHV to a Higher Heating
Value (HHV) unit, which takes into account this
inefficiency of natural gas fuel combustion.
2. 1.30 million btu/hr x 1.1 x $3.10/ thousand
ft3 x [1 thousand ft3/1.048 million btu] x 8760
hrs = $36,976
ii.
Determine the supplemental fuel cost to generate
steam not supplied by the turbine, if necessary
(Note: The steam production capability can also
be obtained from the vendor, along with the additional
heat requirements for supplemental firing to produce
excess steam. In this example, it was determined
that 626,310 btu/hr of additional heat would be
required to produce the 500 lbs/hr of required steam):
1.
Fuel Flow Output (thousand btu/hr) x Natural Gas
Heat Value Correction x Price Fuel ($/thousand
ft3) x Energy Content of Fuel (thousand ft3/btu)
x Period (hrs/yr)
2. 0.626310 million btu/hr x 1.1 x $3.10/ thousand
ft3 x [1 thousand ft3/1.048 million btu] x 8760
hrs= $17,852
iii.
Calculate fuel cost sub-total: $36,976 + $17,852
= $54,828
iv.
Obtain standby power charge from power provider
(utilities assess this infrastructure charge to
provide back-up power capability) and calculate
annual standby fee: $3.00/kW/month x 12 months x
100 kW= $3,600
v.
Calculate maintenance cost (estimated $/kW maintenance
cost can be obtained from microturbine vendor):
$0.01 $/kWh x 100kW x 8760 hrs/yr= $8,760
vi.
Total for DE is $54,828 + $3,600 + $8,760= $67,188
c.
Determine Annual Energy Cost Savings
i.
Savings cost calculation: Current Energy Cost per
Year - DE Fuel Cost per Year
ii. $112,555 - $67,188 = $45,367
d.
Determine the time required to pay off the project.
The Simple Payback Method provides an estimate by
dividing the investment by the periodic project savings.
Payback periods tend to vary by segment: 10-12 years
for institutions and 10-20 years for utilities. For
residential and businesses, especially if the costs
are incorporated into a mortgage, the payback may
be as much as 30 years. Typically, however, payback
for residential and businesses tends to be in the
5 year range.
i.
Obtain the total installed cost from the manufacturer
or the DE Calculator.
The microtubine with heat recovery considered here
costs $90,000.
ii. In this case the payback is $90,000/$45,367
= 1.98 years to payback capital.
Table
2: Summary of Example Simple Payback Method Calculation
| |
Current |
DE
Installed |
| Equipment |
Existing
Boiler |
Combustion
Turbine- cogeneration |
| Electric
Usage (kWh) |
100
kW |
100kW |
| Steam
Usage (lbs/hr) |
500 |
500 |
| Electric
Cost ($ per yr) Rate x hourly usage x hrs in year |
$96,360 |
$36,976 |
| Steam
Cost $ per yr)Rate x hourly usage x hrs in year |
$16,195 |
$17,852 |
| Other
costs |
0 |
$12,360 |
| (Maintenance,
standby charges) |
|
|
| Total |
$112,555 |
$67,966 |
| Savings |
$112,555
- $67,188 = $45,367 |
| Project
Capital Cost |
$90,000 |
| Simple
payback |
$90,000/$45,367=
1.98 years |
There
are excellent references in the links
to economics or you can ask others specific questions
in the Discussion
Forum if you wish to complete a more complex economic
analysis. Many organizations have internal models for
analyzing capital cost decisions. Without these models,
it is even more important to model the system efficiency
correctly. Many manufacturers will provide white papers
on project economics. The more complex analysis would
take into account factors such as internal rates of
return, projected fuel prices over the useful life of
the DE equipment, costs of operations including rates
for skilled service personnel, the rate the customer
will pay to cover the fixed costs of the system when
they are generating power, and the cost of other fixed
grid access charges if necessary.
Using
current technology, the cost to produce a kWh of electricity
for the average small user, such as the residential
and small business customer, will be higher than utility
supplied power unless heat recovery is employed. Consequently,
a decision to employ DE technologies would have to incorporate
other economic factors such as the value of reliability,
which is an extremely important factor to which high
cost value is often applied, and power quality, or include
non-economic factors like the preference for renewable
or environmentally benign power.
Compared
to the average small energy user, commercial and small
industrial customers have a wider range of technologies
from which to choose as well as lower fuel costs and
somewhat lower electric rates. Thermal requirements
allow the DE economics to improve with the capture of
waste heat and resultant reduction in gas usage by reducing
use of boilers or chillers on site. The availability
of new technologies such as microturbines and fuel cells,
which have a higher recoverable heat value for smaller
scale systems than reciprocating engines, will expand
the potential for combined heat and power. Reliability
and power quality add greater potential value to DE
resources for this market segment as well.
Large
industrial customers have a wide array of available
technologies with lower capital costs than those available
for the smaller-scale customers. At the same time, the
larger customer can often purchase fuel at prices close
to those realized by electric utilities. Further, there
are many more heat recovery applications. DE is easy
to justify for these customers on a payback basis alone.
For this reason, a significant DE market currently exists
for large industrial customers.
As
suggested above, reliability is an important issue to
consider when evaluating DE economics. At the consumer
level, power quality has become an increasingly important
issue as appliances like VCRs, digital clocks and computers
have gained widespread acceptance in the marketplace.
Momentary interruptions in the flow of electricity,
not noticed before, became obvious when it was necessary
to reset the blinking clocks every time such an outage
occurred.
The
electric grid system has electromechanical components
that operate on a regular basis in response to unexpected
short circuit events that lead to instantaneous power
disruptions. For instance, two lines touch in high winds
causing a breaker that detects the momentary short circuit
to open the line. The breaker closes almost instantaneously,
and as the short circuit lasted 1/6th of a second, it
is difficult to notice the almost instantaneous interruption.
Nonetheless, a momentary outage occurred. The early
VCR and digital clocks could not tolerate even this
brief of an interruption.
Recent
economic studies of electric reliability requirements
reveal that the "3 nines" U.S. bulk power
standard, which dictates that electric grid power should
be 99.9 % reliable, is unacceptable to a growing
number of commercial customers. The information and
service economy, with Internet communications and server
facilities, in particular, are major drivers for improved
electric power reliability. Some Internet facilities
require "6 nines," or 99.9999 % reliability
while many high-cost process manufacturers and some
service industries now require "5 nines" of
reliability.
System
Savings
The
concepts of system savings or improvements in reliability
are of great concern to utilities, policy makers and
regulators. Capital savings from a DE installation at
a customer premise would flow from three sources: transmission,
distribution, or central station power plant deferrals.
Depending on congestion, capital cost savings may actually
be greater than a direct kW for kW deferral of transmission
or distribution. When DE is located at or close to load,
the transmission and distribution (T&D) electrical
resistance or line losses are reduced.
There
are two primary considerations when capitalizing line
losses. The obvious element is converting these variable
annual energy losses into an equivalent capital cost.
The second element is the increase in generation that
is necessary to make up for the lost power. Peak line
losses for some distribution feeders during peak periods
may be as high as 16 % while average values are
more likely to be five to eight percent. In a simplistic
analysis, the potential system savings are roughly equal
to the capital cost of the DE equipment.
Figure
I below depicts the basic engineering design and economics
of the electricity delivery infrastructure, which provides
the context for assessing the attractiveness of DE use.
In the current predominant configuration, generation
is located at a considerable distance from most of the
load it serves. It must move over increasingly small
(lower voltage) wires to reach the customer. Losses
to residential and small commercial customers are higher
than those of transmission connected industrial customers.
Figure
I: T&D Capital Costs and Peak Line Losses
Source:
DTE Energy Technologies
The
typical electric customer is located some distance from
the power plants. Electric power leaving the generation
station is stepped-up to a high voltage (230kV to 765kV)
to keep losses to a minimum. Except for the very largest
customers, the voltage must be reduced to a lower level
as the power delivery system nears the customer.
In
order to create the infrastructure to deliver electricity,
capital cost is incurred to build the wires and maintenance
costs must be incurred to keep them operating. Moreover,
the longer the distances and the lower the voltages
over which the electricity travels, the greater the
line losses. By the time electricity reaches the typical
small residential or commercial consumer, the utility
will have invested $400-$500 per kW in capital and several
cents per kWh in maintenance costs to keep the physical
assets in operation. Although average energy losses
in delivery of electricity are five to seven percent,
peak losses to the individual residence or small business
may be as much as 13-16 % of electricity that left the
generator. All of these costs and line losses are reflected
in the price the customer pays. That is, the full cost
of the line and the total cost of the energy as generated
will be covered by the charges customers pay for energy
as used.
|
|